Question: Do Ch 5 Homework Saved Problem 5-5 (Algo) 1 13 points Your project to obtain charitable donations is now 37 days into a planned 47-day

Do Ch 5 Homework Saved Problem 5-5 (Algo) 1 13

Do Ch 5 Homework Saved Problem 5-5 (Algo) 1 13 points Your project to obtain charitable donations is now 37 days into a planned 47-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 33 days of the project and to bring in $25,200. Even though we are 37 days into the project, we still see that we have only 89% of this activity complete. The second activity relates to company donations and is scheduled to run for 37 days starting on day 4 and extending through day 41. We estimate that, even though we should have (33/37) 89.19% of this activity complete, it is actually only 60% complete. This part of the project was scheduled to bring in $150,200 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,400. So far $175,700 has actually been brought in on the project. eBook Calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (Negative values should be indicated by a minus sign. Do not round intermediate calculations. Round your dollar amounts to the nearest whole number. Round your "performance index" values to 3 decimal places.) References Schedule variance Schedule performance index Cost variance Cost performance index

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!