Question: Documents that are created prior to or at the start of the project that address strategic, business, or high-level information about the project are referred
Documents that are created prior to or at the start of the project that address strategic, business, or high-level information about the project are referred to as strategy artifacts. All of the following would be considered a strategy artifact with the exception of: Question 7 options: business case stakeholder register project charter project brief