Question: Doing activities in parallel that would normally be done sequentially in order to achieve project objectives or to deal with resource allocation problems is called
Doing activities in parallel that would normally be done sequentially in order to achieve project objectives or to deal with resource allocation problems is called
Accelerating
Fast Tracking
Crashing
Objectives management