Question: dont do part a or b do questions 10. The project described in the following table is scheduled to be completed in II weeks. Construct

10. The project described in the following table is scheduled to be completed in II weeks. Construct a network diagram using AOA or AON (see Example 5 for either fype). Then answer the follow. ing questions: a. If you were the manager of this project, would you be concerned? Explain. b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least 55,000? Chapter 17 , problem 10 What is the probability that the project can be completed in week 11? \begin{tabular}{|l|} \hline 0.13 \\ 0.25 \\ 0.31 \\ 0.81 \\ \hline \end{tabular} QUESTION 15 Chapter 17, problem 10 If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000