Question: dont draw gantt chart A 4 1 2 B 4 3 4 4. A project activities and related information are given in the following table.

dont draw gantt chart dont draw gantt chart A 4 1 2 B 4 3 4 4. A
A 4 1 2 B 4 3 4 4. A project activities and related information are given in the following table. Time Estimates (weeks) Activity Predecessor Optimistic time Most likely time Pessimistic time (b) (a) (m) 7 6 5 2 2 2 E 5 F 3 9 G DE 2 5 a) Draw a Gantt chart. b) Draw the AON network and compute the slack for each activity. c) What is the probability that the project will be completed in 12 weeks or more? D A 4 D 6 8