Question: Dont quite understand the process. Please help. Given the following project matrix and network Diagram Task Predecessors Duration Days A 5 B A 3 C
Dont quite understand the process. Please help.
- Given the following project matrix and network Diagram
| Task | Predecessors | Duration Days |
| A |
| 5 |
| B | A | 3 |
| C | A | 4 |
| D | B,C | 2 |
| E | D | 3 |

What is the total slack for task B?
- -1
- 0
- 1
- 1.2