Question: DR. P is considering a new project based on the information below. What is the Expected NPV of the project? WACC for the project
DR. P is considering a new project based on the information below. What is the Expected NPV of the project? WACC for the project 0.080. data in thousands 0 1 2. 3 Initial costs 3,334 Prob Scenario 1 30% 2,085 2,085 2,085 Scenario 2 60% 1,412 1,412 1,412 Scenario 3 10% -477 -477 -477