Question: Draw a corresponding AON network Compute ES and EF for each activity. Compute LS and LF for each activity. Find the critical path. Determine the

Draw a corresponding AON network
Compute ES and EF for each activity. Compute LS and LF for each activity. Find the critical path.
Determine the total slack and free slack.
b. Predecessor Duration Activity A 3 B A 8 B 9 D 3 E B 2 F 4 E, H A G 6 H G 5 J D, F 1Step by Step Solution