Question: Draw a Network Diagram and determine the time required for this project. Task Duration Days Dependency A 3 B 5 A C 4 B D

Draw a Network Diagram and determine the time
Draw a Network Diagram and determine the time
Draw a Network Diagram and determine the time required for this project. Task Duration Days Dependency A 3 B 5 A C 4 B D 6 B E 7 F 9 D G 2. F H 4. E,G 21 days 24 days 29 days o 25 days Draw a Network Diagram. Do a forward and backward pass to determine the float in Task E. Task Duration Days Dependency A 3 B 5 A 4 B D 6 B E 7 F 9 D G 2 F H 4 E EG O days (in critical path) 4 days 6 days 8 days