Question: Draw a Network Diagram and determine the time required for this project. dency 21 days 24 days 29 days 25 days Draw a Network Diagram.

Draw a Network Diagram and determine the timeDraw a Network Diagram and determine the time

Draw a Network Diagram and determine the time required for this project. dency 21 days 24 days 29 days 25 days Draw a Network Diagram. Do a forward and backward pass to determine the float in Task E. 0 days (in critical path) 4 days 6 days 8 days