Question: -Draw a network model by hand and complete the schedule through forward and backward calculations. -Propose SLACK and main path (CP) -You must determine the

-Draw a network model by hand and complete the

-Draw a network model by hand and complete the schedule through forward and backward calculations. -Propose SLACK and main path (CP) -You must determine the specific completion date yourself and find the probability

Activity Activity time (days) Optimism Top priority 8 10 5 8 Pessimism Predecessor work 12 00 D 17 8 9 D 100 EUR 2 3 B E 10 12 F 6 7 G 1 3 5 A,C D,E DE F,G G H H 2 5 4 1 J 2 4 N0000 5 K 2 2 H