Question: Draw a Precedence Diagram Method (PDM) diagram using the data from Table 1 below Fill in the calculations in the table below incorporating all relevant

Draw a Precedence Diagram Method (PDM) diagram

Draw a Precedence Diagram Method (PDM) diagram using the data from Table 1 below Fill in the calculations in the table below incorporating all relevant information from the diagram (42 marks) b) Identify the critical path (4 marks) c) Record the project duration (4 marks) Table 1 Activity Duration Predecessor ES EF LS LF TF FF 2 B 7 A 10 A D 4 A 6 B E F G 5 B,C 8 CD H 9 D 1 12 F,G J 5 F K 5 E,J L 6 GH M 4 FH N 3 IK,L,M

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!