Question: Draw a project network diagram for a research project from the following information. Use this information to answer questions 27 through 30. In the project
Draw a project network diagram for a research project from the following information. Use this information to answer questions 27 through 30.
In the project network diagram for the research project what activity is a burst activity?
Select one:
A.
Activity E
B.
Activity H
C.
Activity G
D.
Activity C
Question:In the project network diagram for the research project what activity is a merge activity?
Select one:
A.
Activity C
B.
Activity G
C.
Activity H
D.
Activity B
Question Identify the critical path for the research project
Select one:
A.
A-B-C-D-G-H
B.
A-B-C-E-G-H
C.
A-B-C-F-G-H
D.
None
Question: Calculate the Earliest Start Date (ES) for activity G in the research project
Select one:
A. 10
B. 11
C. 12
D. 13
Draw a project network diagram for a research project from the following information. Use this information to answer questions 27 through 30
Step by Step Solution
There are 3 Steps involved in it