Question: Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical Path ID Activity Predecessor
Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical Path
| ID | Activity | Predecessor | Time |
| A | Order Review | None | 2 |
| B | Order standard parts | A | 3 |
| C | Produce standard parts | A | 10 |
| D | Design custom parts | A | 13 |
| E | Software development | A | 18 |
| F | Manufacture custom hardware | C,D | 15 |
| G | Assemble | B,F | 10 |
| H | Test | E,G | 5 |