Question: please answer this The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this

please answer thisplease answer this The project information for

The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this project. Compute the early and late activity times and slack times. Identify the critical path. Predecessor Time ID Description A Order review None 2 A 3 Order standard parts Produce standard parts 10 D 13 E Design custom parts Software development Manufacture custom hardware A 18 F 15 G Assemble CD B, F E, G 10 H Test 5