Question: Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical Path ID Activity Predecessor
Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical Path
| ID | Activity | Predecessor | Time |
| A | Prepare Site | None | 2 |
| B | Pour Foundation | A | 3 |
| C | Erect Frame | B | 4 |
| D | Roof | C | 4 |
| E | Windows | C | 1 |
| F | Doors | C | 1 |
| G | Electrical | C | 3 |
| H | Rough-In-Time | D,E,F,G | 2 |
| I | Door Opener | D,E,F,G | 1 |
| J | Paint | H,I | 2 |
| K | Cleaner | J | 1 |