Draw a project network from the following

Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity? 1 ID Predecessor A None B 3 points B D None E C, D What type of activity is each of the following? Activity A Neither Burst nor Merge v Activity B Burst Activity C Burst Activity D (Click to select) Activity E Merge (Click to select) Neither Burst nor Merge Merge Burst Both Burst and Merge