Question: Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity? ID Predecessor A None A

Draw a project network from the following

Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity? ID Predecessor A None A B MOOWO I None E D, F, G What type of activity is each of the following? Activity A Burst Activity B Neither Burst nor Merge Activity C Neither Burst nor Merge Activity D Neither Burst nor Merge Activity E Burst Activity F Merge Activity G Neither Burst nor Merge Activity Merge