Question: Draw a project network given the following information. ( 1 0 points ) Complete the forward and backward pass compute activity slack ( 5 points

Draw a project network given the following information. (10 points)
Complete the forward and backward pass compute activity slack (5 points)
Identify the critical path. (2.5 points)
Create a Gantt Chart for the project (10 points)
How long is the project expected to take? (2.5 points)
\table[[ID,Description,Predecessor,Time],[A,Survey,None,5],[B,Soils report,A,20],[C,Traffic design,A,30],[D,Lot layout,A,5],[E,Approve design,B. C. D,80],[F,Illumination,E,15],[G,Drainage,E,30],[H,Landscape,E,25],[I,Signige,E,],[J,Bid proposal,F. G. H.1,10]]
 Draw a project network given the following information. (10 points) Complete

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!