Question: Draw activity on node diagram for the Activity Predecessor Duration(weeks) following project and find: A 20 Project Duration. B A 8 . . . .

 Draw activity on node diagram for the Activity Predecessor Duration(weeks) following
project and find: A 20 Project Duration. B A 8 . .

Draw activity on node diagram for the Activity Predecessor Duration(weeks) following project and find: A 20 Project Duration. B A 8 . . . . C A 6 Critical Path. D B 12 E C 16 What is the duration of project if the F C 18 activity I delay 2 weeks. G D 16 . . H D, E, F 10 F 10 G. H. I 12