Question: hand written please Precedence Diagram Method (PDM) Activity on Node (AON) Draw the network and calculate the following. 1. Forward Path 2. Backward Path 3.

hand written please
hand written please Precedence Diagram Method
Precedence Diagram Method (PDM) Activity on Node (AON) Draw the network and calculate the following. 1. Forward Path 2. Backward Path 3. Critical Activities 4. Critical Path 5. Total Float 6. Free Float Q:1 Activity ID IPA Duration Logic 5 FSI, FF10 FS2, FF2 A B C D E FS5 A 8 B 10 B 20 13 D D 3 E SS10, FSO SS7 F FF5 SS10, SF10 Q2: Activity ID IPA Duration Logic A 10 B 12 FSO, FFS B 20 SF10, SS10 D 8 FS1 E B 8 FF10 F SSI, FS1 F A 9 SS10, FS1 G D 11 FSO E FS7, FF5