Question: DRAW Activity-On-Arrow (A-O-A) Network ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A ___ 5 B A 2 C A 4 D B 5 E B 5 F

DRAW Activity-On-Arrow (A-O-A) Network

ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS)
A ___ 5
B A 2
C A 4
D B 5
E B 5
F C 5
G E,F 2
H D 3
I G,H 5