Question: Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total
Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total float
| Activity | description | immediate predecessor | Expected time (Weeks) |
| A | - | 5 | |
| B | - | 4 | |
| C | A | 7 | |
| D | B | 7 | |
| E | B | 8 | |
| F | B | 5 | |
| G | C,D | 8 | |
| H | E,I | 11 | |
| I | F | 2 | |
| J | F | 12 | |
| K | H,I | 11 |
2.convert the above into activity on the node
Step by Step Solution
There are 3 Steps involved in it