Question: Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total

Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total float

Activity description immediate predecessor Expected time (Weeks)
A - 5
B - 4
C A 7
D B 7
E B 8
F B 5
G C,D 8
H E,I 11
I F 2
J F 12
K H,I 11

2.convert the above into activity on the node