Question: Draw an AON (Activity On Node) network diagram representing all project activities, making sure to label activities and their durations. Find the total slack for
- Draw an AON (Activity On Node) network diagram representing all project activities, making sure to label activities and their durations.
- Find the total slack for each activity.

Activity Predecessors Optimistic Most likely Duration Duration A B C D E F G H I J - A, B A C B, C D, E E, F F, G 7 6 6 5 7 5 8 4 6 8 10 10 11 10 15 7 9 6 7 9 Pessimistic Duration 19 14 22 21 17 15 16 8 14 10