Question: Draw Gantt CHART Act ID Activity Description Duration (weeks) Immediate Predecessor Relationship Lag (weeks) P Planning & Procurement P1 Determine equipment needs 6 - -
Draw Gantt CHART
| Act ID | Activity Description | Duration (weeks) | Immediate Predecessor | Relationship | Lag (weeks) |
| P | Planning & Procurement | ||||
| P1 | Determine equipment needs | 6 | - | - | - |
| P2 | Obtain vendor proposals | 8 | - | - | - |
| P3 | Select vendor | 4 | P1,P2 | FS,FS | 2,1 |
| P4 | Order system | 10 | P3 | FS | 0 |
| D | Design & Installation | ||||
| D1 | Design new warehouse layout | 10 | P3 | FS | 1 |
| D2 | Design warehouse | 6 | D1 | FF | 5 |
| D3 | Design computer interface | 6 | P3 | FF | 2 |
| D4 | Interface computer | 6 | P4,D2,D3 | FS,SS,FF | 2,3,3 |
| D5 | Install system | 6 | P4,D2 | FS,FS | 3,3 |
| S | Start Up | ||||
| S1 | Train system operators | 4 | D4 | FS | 2 |
| S2 | Test system | 4 | D5,S1 | FS,FS | 0,1 |