Question: Draw Gantt CHART Act ID Activity Description Duration (weeks) Immediate Predecessor Relationship Lag (weeks) P Planning & Procurement P1 Determine equipment needs 6 - -

Draw Gantt CHART

Act

ID

Activity Description

Duration (weeks)

Immediate Predecessor

Relationship

Lag (weeks)

P

Planning & Procurement

P1

Determine equipment needs

6

-

-

-

P2

Obtain vendor proposals

8

-

-

-

P3

Select vendor

4

P1,P2

FS,FS

2,1

P4

Order system

10

P3

FS

0

D

Design & Installation

D1

Design new warehouse layout

10

P3

FS

1

D2

Design warehouse

6

D1

FF

5

D3

Design computer interface

6

P3

FF

2

D4

Interface computer

6

P4,D2,D3

FS,SS,FF

2,3,3

D5

Install system

6

P4,D2

FS,FS

3,3

S

Start Up

S1

Train system operators

4

D4

FS

2

S2

Test system

4

D5,S1

FS,FS

0,1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!