Question: Act ID Activity Description Duration (weeks) Immediate Predecessor Relationship Lag (weeks) P Planning & Procurement P1 Determine equipment needs 6 - - - P2 Obtain

| Act ID | Activity Description | Duration (weeks) | Immediate Predecessor | Relationship | Lag (weeks) |
| P | Planning & Procurement |
|
|
|
|
| P1 | Determine equipment needs | 6 | - | - | - |
| P2 | Obtain vendor proposals | 8 | - | - | - |
| P3 | Select vendor | 4 | P1,P2 | FS,FS | 2,1 |
| P4 | Order system | 10 | P3 | FS | 0 |
| D | Design & Installation |
|
|
|
|
| D1 | Design new warehouse layout | 10 | P3 | FS | 1 |
| D2 | Design warehouse | 6 | D1 | FF | 5 |
| D3 | Design computer interface | 6 | P3 | FF | 2 |
| D4 | Interface computer | 6 | P4,D2,D3 | FS,SS,FF | 2,3,3 |
| D5 | Install system | 6 | P4,D2 | FS,FS | 3,3 |
| S | Start Up |
|
|
|
|
| S1 | Train system operators | 4 | D4 | FS | 2 |
| S2 | Test system | 4 | D5,S1 | FS,FS | 0,1 |
Draw a precedence / Activity on Node (AON) diagram of the given activities in the table above.
a) Find project completion time.
b) Identify the critical path of the project. List down all critical activities and give your opinion to the client on the project. -------------------------
ACT Activity Description Duration Immediate (weeks) Predecessor Relationship Lag (weeks) ID P Planning & Procurement Determine equipment needs PI 5. P2 Obtain vendor proposals P3 Select vendor 4 P1, P2 FS,FS P4 Order system 10 P3 FS 10 P3 FS 1 FF 5 5 FF DI P3 P4,02.03 2 D Design & Installation DI Design new warehouse layout D2 Design Warehouse D3 Design computer interface Interface computer DS install system S Start Up SI Train system operators 52 Test system 5 FS,SS, FF 2,3,3 82 6 P4,02 FS, FS 3,3 4 04 2 FS FS,FS DS,S1 0,1 Draw a precedence / Activity on Node (ADN) diagram of the given activities in the table above. a) Find project completion time. b) Identify the critical path of the project. List down all critical activities and give your opinion to the client on the projectStep by Step Solution