Question: Draw precedence diagramming Method (PDM) network diagram precision = predecessor Find early start, late start, early finish, late finish and Critical Path. FS = Finish

 Draw precedence diagramming Method (PDM) network diagram precision = predecessor Find

Draw precedence diagramming Method (PDM) network diagram

precision = predecessor

Find early start, late start, early finish, late finish and Critical Path.

FS = Finish to Start

FSx = Finish to Start with x day lag time

SSx = Start to Start with x day