Question: Question 1 Find the critical path using the critical path method for activities shown in Table 1. Correctly represent the network diagram with activity

Question 1 Find the critical path using the critical path method for activities shown in Table 1. Correctly represent the network diagram with activity name, early start (ES), early finish (EF), late start (LS), late finish (LF), and duration. See Figure 1 for legend) and precedence relationships (arrows from/to activities). In answering this question, if you need to make any assumptions in addition to the information provided to you, you need to EXPLICITLY state them. Problem assumption: Start date is 0 for forward pass. Table 1 Duration Predecessors Activity A 2 days 3 days - B A C 1 days A D 2 days A E 1 days C F 1 days B G 3 days D, E, F Figure 1 - Legend for Activities in Network Diagram Early Early Start Late Start Duration Activity Finish Late Finish 1.1 Draw the network diagram along with activity name, early start (ES), early finish (EF), late start (LS), late finish (LF), and duration. 1.2 Write the critical path based on your analysis using the network diagram above (e.g. A-C-F- I). 1.3 What is the total project duration? 1.4 What happens to other tasks if B takes six days to complete? Is there any impact on the project duration? 1.5 How much longer duration C can take without any impact on the total project duration?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
