Question: Draw produc t structure diagram for final product. Prepare MRP for component B. Child Items Lead time Current Inventory Final product 1 week 25 A

Draw producDraw produc t structure diagram for finalt structure diagram for final product. Prepare MRP for component B.

Child Items Lead time Current Inventory Final product 1 week 25 A (3 required) B (2 required) C (2 required) B (3 required) C(1 required) A 1 week none B none 2 weeks 200 none 1 week none The MPS for final product: Week Number 1 2 3 4 5 6 Quantity 0 0 0 75 100 125