Question: Draw the activity on node (AON) project network for the construction project with activities A through H. - What are the critical activities and how


Draw the activity on node (AON) project network for the construction project with activities A
through H.
- What are the critical activities and how long is the critical path?
( Note: - Activities G and H are the last two activities to be completed. You can connect them to the 'End' activity.
Start activity begins with activity 'A'.
( Please note that you do not have to calculate the ES, EF, LS, LF values for each node in a simple network to
determine the critical path. )
( You can add up durations for the 3 alternate paths in the network. The longest path is the critical path. )
- 3.5 Draw the activity-on-node (AON) project network associated with the following activities for Carl Betterton's construction project. How long should it take Carl and his team to complete this project? What are the critical path activities? 3: Project Management ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A 3 B D 4 A 6 D B 6 E B 4 F c 4 G D 6 H E, F 8Step by Step Solution