Question: Problem 3.5 - Draw the activity on node (AON) project network for the construction project with activities A through H. - What are the critical
Problem 3.5 - Draw the activity on node (AON) project network for the construction project with activities A
through H.
- What are the critical activities and how long is the critical path?
( Note: - Activities G and H are the last two activities to be completed. You can connect them to the 'End' activity.
Start activity begins with activity 'A'.
( Please note that you do not have to calculate the ES, EF, LS, LF values for each node in a simple network to determine the critical path. )
( You can add up durations for the 3 alternate paths in the network. The longest path is the critical path. )
| ACTIVITY | IMMEDIATE PREDECESSOR(S) | TIME (DAYS) |
|---|---|---|
| A | 3 | |
| B | A | 4 |
| C | A | 6 |
| D | B | 6 |
| E | B | 4 |
| F | C | 4 |
| G | D | 6 |
| H | E, F | 8 |