Question: Problem 3.5 - Draw the activity on node (AON) project network for the construction project with activities A through H. - What are the critical

Problem 3.5 - Draw the activity on node (AON) project network for the construction project with activities A

through H.

- What are the critical activities and how long is the critical path?

( Note: - Activities G and H are the last two activities to be completed. You can connect them to the 'End' activity.

Start activity begins with activity 'A'.

( Please note that you do not have to calculate the ES, EF, LS, LF values for each node in a simple network to determine the critical path. )

( You can add up durations for the 3 alternate paths in the network. The longest path is the critical path. )

ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS)
A 3
B A 4
C A 6
D B 6
E B 4
F C 4
G D 6
H E, F 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!