Question: Draw the activity on node network for the following project activities: ActivityDurationIPA A5 days- B3 daysA C4 daysA D5 daysA E2 daysB F3 daysB, C
Draw the activity on node network for the following project activities:
ActivityDurationIPA
A5 days-
B3 daysA
C4 daysA
D5 daysA
E2 daysB
F3 daysB, C
G2 daysD, E, F