Question: Draw the activity-on-node project network. Complete forward and backward pass and identify the critical path. Please be clear if by hand draw. UNIN Activities Predecessors

Draw the activity-on-node project network. Complete forward and backward pass and identify the critical path. Please be clear if by hand draw.
UNIN Activities Predecessors Duration A 2 B 2 2 D A, B, C 5 E D 1 F E 1 G F 1 H G 2 I H 2 J G 2 K J 1 L I, K 2 M L 1 N M 2 M 5 P N, O 1 Q P 5 R Q 1 NNStep by Step Solution