Question: Draw the AON ( Activity - On - Node ) project network on a piece of paper before answering these questions. Include the 6 box

Draw the AON (Activity-On-Node) project network on a piece of paper before answering these questions. Include the 6 box rectangle with Activity Letter, Activity Time, ES, EF, LS, LF.
Activity
Immediate Predecessor
Activity Time (days)
A
-
6
B
-
8
C
A, B
5
D
B
4
E
C
7
F
C, D
3
G
D
6
H
E, F, G
5
List the ES, EF, LS, LF for Activity A. Use this format: 1,2,3,4 Note there is a space after the comma.