Question: Draw the corresponding Precedence Diagram for the project schedule information presented in Table 1. Table 1 ID Task description A Contract signed B Site evaluation
Draw the corresponding Precedence Diagram for the project schedule information presented in Table 1. Table 1 ID Task description A Contract signed B Site evaluation C Sample tests Predecessor None A B
Step by Step Solution
There are 3 Steps involved in it