| Act | I.P. | Time | Slack |
| A | --- | 6 | |
| B | ---
| 9 | |
| C | A,B | 7 | |
| D | B | 9 | |
| E | B | 12 | |
| F | C | 9 | |
| G | C | 8 | |
| H | D,G | 4 | |
| I | E | 10 | |
| J | F,H | 5 |