Question: Draw the different paths from the table and select the critical path begin{tabular}{|c|c|c|} hline Activity & Immediatepredecessoractivity & Durationofactivities(Days) hline a & - &

Draw the different paths from the table and select the critical path

Draw the different paths from the table and select the critical path

\begin{tabular}{|c|c|c|} \hline Activity & Immediatepredecessoractivity & Durationofactivities(Days) \\ \hline a & - & 20 \\ \hline b & a & 10 \\ \hline c & b & 8 \\ \hline d & a & 11 \\ \hline e & c,d & 7 \\ \hline f & e & 6 \\ \hline g & d & 12 \\ \hline h & e & 13 \\ \hline i & g,h & 5 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!