Question: Draw the figure using activity on node (AON) and identify the critical activities or Path and the expected completion time. (Rubrics: 05 Marks for correct
- Draw the figure using activity on node (AON) and identify the critical activities or Path and the expected completion time. (Rubrics: 05 Marks for correct diagram, 05 Marks for correct labels, 05 Marks for the critical activity or path and the length of Path and 05 marks for the slack activities.)
| ACTIVITIES | PREDECESSOR | DURATIONS (DAYS) |
| A | NONE | 1 |
| B | NONE | 3 |
| C | NONE | 2 |
| D | NONE | 5 |
| E | NONE | 1 |
| F | A | 3 |
| G | A | 1 |
| H | G, I, J | 2 |
| I | T, E, N | 4 |
| J | K | 3 |
| K | L, M | 2 |
| L | T, E, N | 3 |
| M | NONE | 2 |
| N | NONE | 3 |
| O | H | 2 |
| P | H | 3 |
| Q | O | 2 |
| R | P | 1 |
| S | Q, R | 2 |
| T | F, B, C, D | 7 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
