Question: Draw the figure using activity on node (AON) and identify the critical activities or Path and the expected completion time. (Rubrics: 05 Marks for correct

  1. Draw the figure using activity on node (AON) and identify the critical activities or Path and the expected completion time. (Rubrics: 05 Marks for correct diagram, 05 Marks for correct labels, 05 Marks for the critical activity or path and the length of Path and 05 marks for the slack activities.)

ACTIVITIES

PREDECESSOR

DURATIONS (DAYS)

A

NONE

1

B

NONE

3

C

NONE

2

D

NONE

5

E

NONE

1

F

A

3

G

A

1

H

G, I, J

2

I

T, E, N

4

J

K

3

K

L, M

2

L

T, E, N

3

M

NONE

2

N

NONE

3

O

H

2

P

H

3

Q

O

2

R

P

1

S

Q, R

2

T

F, B, C, D

7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!