Question: Draw the following project schedule Task Aduration 10 days Task Bduration 5 days, the predecessor is task A Task C duration 8 days, the predecessor

Draw the following project schedule

Task Aduration 10 days

Task Bduration 5 days, the predecessor is task A

Task C duration 8 days, the predecessor is task A

TaskD duration 15 days, the predecessor is task B

Task E duration 10 days, the predecessor is task B

Task F duration 2 days, the predecessor is task C

Task G duration 10 days, predecessors are tasks D, E, and F

Indicate the ES, EF, LS, LF and float time on the diagram itself

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!