Question: Draw the following project schedule Task Aduration 10 days Task Bduration 5 days, the predecessor is task A Task C duration 8 days, the predecessor
Draw the following project schedule
Task Aduration 10 days
Task Bduration 5 days, the predecessor is task A
Task C duration 8 days, the predecessor is task A
TaskD duration 15 days, the predecessor is task B
Task E duration 10 days, the predecessor is task B
Task F duration 2 days, the predecessor is task C
Task G duration 10 days, predecessors are tasks D, E, and F
Indicate the ES, EF, LS, LF and float time on the diagram itself