Question: Draw the forward pass and backward pass (Need to Include ES,LS,EF,LF) and identify the critical path for the following. Project start date 1 June 2021
Draw the forward pass and backward pass (Need to Include ES,LS,EF,LF) and identify the critical path for the following.
Project start date 1 June 2021
Project end date 1 Dec 2021
Number of days 131 days (excluding Saturday and Sunday

Formula
EF= ES+Duration
LS= LF-Duration
Activity B C D E F G H J Duration 7 13 KL M N O 13 3 15 15 8 5 10 15 8 2 5 2 2 2 CD DEF G H J,K L M Predecessors I | L M NStep by Step Solution