Question: Draw the forward pass and backward pass (Need to Include ES,LS,EF,LF) for the following. Project start date 1 June 2021 Project end date 1 Dec

Draw the forward pass and backward pass (Need to Include ES,LS,EF,LF) for the following.

Project start date 1 June 2021

Project end date 1 Dec 2021

Number of days 131 days (excluding Saturday and Sunday)

Draw the forward pass and backward pass (Need to

Activity Duration A B C D E F B C D F G H I J K L M N O 7 3 13 3 15 15 10 8 5 8 15 2 5 2 2 2 A B C D E F H H I, K Predecessors G L M N