Question: Draw the network and identify the critical path. Also calculate the earliest and latest starting and finishing times for each activity. Activity Preceding Activity Time
Draw the network and identify the critical path. Also calculate the earliest and latest starting and finishing times for each activity.
| Activity | Preceding Activity | Time (weeks) |
| A | 4 | |
| B | 6 | |
| C | A,B | 7 |
| D | B | 8 |
| E | B | 5 |
| F | C | 5 |
| G | D | 7 |
| H | D,E | 8 |
| I | F,G,H | 4 |