Question: Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time. Activity Immediate Predecessor(s) Time

Draw the network corresponding to the following

Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 IB 14 C A 16 D B 9 E 6 F C D 16 G D, E 18 GF 19 Activity Earliest Start Earliest Finish Latest Start Latest Finish Slack A B C ID IE JF IG