Question: Immediate Time Required Activity Predecessors (weeks) A 1 Start 2 B l Start 3 C l A, B 2 D l B 4 E C

 Immediate Time Required Activity Predecessors (weeks) A 1 Start 2 Bl Start 3 C l A, B 2 D l B 4

Immediate Time Required Activity Predecessors (weeks) A 1 Start 2 B l Start 3 C l A, B 2 D l B 4 E C 3 F D, E 2 For the project described by the above table do the following: (a) Draw the network diagram, and (b) Clearly indicate the sequence of activities on the critical path and compute the length of the critical path. The table below indicates the feasibility of crashing each of the activities in this project and the related costs per week. Activity Time Required Minimum Feasible Cost per weeks Time weeks Week A 2 1 $1000 B 3 2 $1500 C 2 2 - D 4 2 $2000 E 3 2 $1750 F 2 2 - (c) If this project must be completed in 8 weeks, clearly explain the least expensive way to accomplish this. (d) Returning to the original project of parts (a) and (b), it has been determined that the task completion times for task C have the following distribution: Time Required Probability (weeks) 0.5 0.2 l 0.2 2 0.2 What is the corresponding distribution of project completion times

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!