Question: Draw the network diagram, calculate critical path & slack. Task # Activity 1 Preheat oven 2 Assemble ingredients 3 4 5 6 7 8 9

Draw the network diagram, calculate critical path & slack.

Draw the network diagram, calculate critical path

Task # Activity 1 Preheat oven 2 Assemble ingredients 3 4 5 6 7 8 9 10 11 12 13 14 Melt chocolate Beat eggs & butter Grease & flour pan Mix in dry ingredients Add chocolate Add nuts Put batter into pan Bake Cool Make frosting Frost Serve Duration (minutes) 20 5 10 5 3 4 3 3 385 260 20 15 10 Precedents INN -- 2 2 -- 4 3,6 6 5, 7, 8 1,9 10 2 11, 12 13