Question: Draw the network diagram from the information given below ) identify the critical path and determine the project completion time. Also find (ii) the earliest

Draw the network diagram from the information

Draw the network diagram from the information given below ) identify the critical path and determine the project completion time. Also find (ii) the earliest start, earliest finish, latest start and latest finish times, and (iii) total float and free float Activity A B C D E F G H I J K L M Immediate A B BD DE F G GHICK IL predecessor Time (days) 16 11 14 9 12 10 30 19 117 40 9 14 (iv) What would happen if D is completed 2 days earlier, while C and Lare delayed by 1 day each