Question: Draw the node network, perform the CPM calculations, and mark the critical path for the table below: Activity Duration IPA ES EF LS LF TF

Draw the node network, perform the CPM calculations, and mark the critical path for the table below:

Activity Duration IPA ES EF LS LF TF FF
A 3 -- 0 3 0 3 0 0
B 7 A 3 10 3 10 0 0
C 4 A 3 7 6 10 3 3
D 5 B 10 15 13 18 3 3
E 8 B,C 10 18 10 18 0 0

Show all calculations!