Question: Draw the node network, perform the CPM calculations, mark the critical path, and complete the table below: Activity Duration Preceding Activity Relationship Lag ES EF
Draw the node network, perform the CPM calculations, mark the critical path, and complete the table below: Activity Duration Preceding Activity Relationship Lag ES EF LS LF FF TF FloatA 4 ? FS 0 B 3 ? FS 0 C 8 A SF 0 D 7 A, B FS 0 E 6 D SS 3 F 3 D FS 0 G 5 F SS 2 2 F FF 0 How many days will it take to complete the project?