Question: Draw the node network, perform the CPM calculations, mark the critical path, and complete the table below: Preceding Activity Duration Activity Relationship Lag ES EF

 Draw the node network, perform the CPM calculations, mark the critical
path, and complete the table below: Preceding Activity Duration Activity Relationship Lag

Draw the node network, perform the CPM calculations, mark the critical path, and complete the table below: Preceding Activity Duration Activity Relationship Lag ES EF LS LF FF TF Float A 4 FS 0 B 3 FS 0 C 8 A SF 0 D 7 A, B FS 0 E 6 D SS 3 3 D FS 0 G 5 F SS 2 2 F FF 0 How many days will it take to complete the project