Question: Draw the PERT diagram Given Activity Predecessor A - 8 A C A D E Duration (days) 3 4 2 5 4 F D,E 2

Draw the PERT diagram Given Activity Predecessor
Draw the PERT diagram Given Activity Predecessor A - 8 A C A D E Duration (days) 3 4 2 5 4 F D,E 2 Use forward and backward pass to determine critical path and duration for the above project based on your PERT Diagram Early Start/Early Finish ES Activity EF Duration LF LS Late Start/Late Finish 2002